# Board of Supervisors Minutes: December 11, 2012

- Meeting date: 2012-12-11
- Document type: minutes
- Pages in official PDF: 24
- [Canonical HTML transcript](https://sfbos.info/documents/78/2012-12-11-minutes)
- [Authoritative City PDF](https://sfgov.legistar.com/View.ashx?M=M&ID=220867&GUID=D69A15C8-960D-4BB8-84CB-B726DFA34068)

> This text was extracted for search and accessibility. The linked City PDF is the authoritative public record.

## Structured legislative records

### File 120982: Jack Early Commemorative Plaque - Stockton Street Adjacent to Washington Square

- Pages: 6-7
- Vote 1: final-passage, likely final
  - Action: 120982 [Jack Early Commemorative Plaque - Stockton Street Adjacent to Washington Square] Sponsor: Chiu Ordinance commemorating the Stockton Street sidewalk adjacent to Washington Square Park under Public Works Code Sections 789 et seq., the Commemorative Street Plaque Ordinance, accepting a plaque in honor of Jack Early as a gift to the City, waiving permit and inspection fees for plaque installation, and directing official acts in furtherance of this Ordinance. FINALLY PASSED by the following vote:
  - Ayes: Avalos, Campos, Chiu, Chu, Cohen, Elsbernd, Farrell, Kim, Mar, Olague, Wiener

### File 121007: Electric System and Solar Project Agreement - North Star Solar, LLC

- Pages: 7
- Vote 1: first-reading
  - Action: 121007 [Electric System and Solar Project Agreement - North Star Solar, LLC] Ordinance authorizing, pursuant to Charter Section 9.118(a), a System Impact Mitigation Agreement with North Star Solar, LLC, requiring North Star Solar, LLC, to pay the Public Utilities Commission the costs necessary to mitigate the impacts to the City’s electric system caused by the interconnection of North Star Solar, LLC’s solar project to the electric grid; authorizing similar mitigation agreements with other projects in the future; appropriating funds from these agreements to pay the costs of mitigation work; and placing various mitigation funds on reserve with the Board of Supervisors. (City Attorney's Office) (Fiscal Impact) PASSED, ON FIRST READING by the following vote:
  - Ayes: Avalos, Campos, Chiu, Chu, Cohen, Elsbernd, Farrell, Kim, Mar, Olague, Wiener

### File 121064: Business and Tax Regulations, Police Codes - Parking Stations - Revenue Control Equipment; License Regulations; Parking Tax Bonds; Administrative Citation Process

- Pages: 7
- Vote 1: first-reading
  - Action: 121064 [Business and Tax Regulations, Police Codes - Parking Stations - Revenue Control Equipment; License Regulations; Parking Tax Bonds; Administrative Citation Process] Sponsor: Campos Ordinance amending the San Francisco Business and Tax Regulations Code by amending Article 6 (Common Administrative Provisions) to revise the bonding requirements for parking operators; revise the time to bring an action to collect tax; clarify the extent of a surety's liability; revise the administrative citation appeal process; and make other minor technical changes; amending Article 22 (Parking Stations; Revenue Control Equipment) to clarify that non-City governmental entities operating parking stations are exempt from the revenue control equipment requirements; and amending the San Francisco Police Code Article 17 (Miscellaneous License Regulations) to clarify that governmental entities operating parking garages or parking lots are exempt from the permitting requirements applicable to other commercial parking garage and valet operations. PASSED, ON FIRST READING by the following vote:
  - Ayes: Avalos, Campos, Chiu, Chu, Cohen, Elsbernd, Farrell, Kim, Mar, Olague, Wiener

### File 121012: Adopting CEQA Findings - Geary Road Bridge Project

- Pages: 7-8
- Vote 1: adoption, likely final
  - Action: 121012 [Adopting CEQA Findings - Geary Road Bridge Project] Resolution adopting findings under the California Environmental Quality Act (CEQA), CEQA Guidelines, and San Francisco Administrative Code Chapter 31, including the adoption of a mitigation monitoring and reporting program, related to the funding of Project No. CUW26403, the Geary Road Bridge Project, in Alameda County and directing the Clerk of the Board of Supervisors to notify the Controller of this action. (Public Utilities Commission) ADOPTED by the following vote:
  - Ayes: Avalos, Campos, Chiu, Chu, Cohen, Elsbernd, Farrell, Kim, Mar, Olague, Wiener

## Extracted text

### [Page 7](https://sfbos.info/documents/78/2012-12-11-minutes#page-7)

Board of Supervisors                           Meeting Minutes - Draft                                            12/11/2012




NEW BUSINESS


Recommendations of the Budget and Finance Committee

121007 [Electric System and Solar Project Agreement - North Star Solar, LLC]
            Ordinance authorizing, pursuant to Charter Section 9.118(a), a System Impact Mitigation
            Agreement with North Star Solar, LLC, requiring North Star Solar, LLC, to pay the Public Utilities
            Commission the costs necessary to mitigate the impacts to the City’s electric system caused by the
            interconnection of North Star Solar, LLC’s solar project to the electric grid; authorizing similar
            mitigation agreements with other projects in the future; appropriating funds from these agreements
            to pay the costs of mitigation work; and placing various mitigation funds on reserve with the Board
            of Supervisors. (City Attorney's Office)
            (Fiscal Impact)
            PASSED, ON FIRST READING by the following vote:
                 Ayes: 11 - Avalos, Campos, Chiu, Chu, Cohen, Elsbernd, Farrell, Kim, Mar, Olague, Wiener


121064 [Business and Tax Regulations, Police Codes - Parking Stations - Revenue Control
       Equipment; License Regulations; Parking Tax Bonds; Administrative Citation
       Process]
            Sponsor: Campos
            Ordinance amending the San Francisco Business and Tax Regulations Code by amending Article
            6 (Common Administrative Provisions) to revise the bonding requirements for parking operators;
            revise the time to bring an action to collect tax; clarify the extent of a surety's liability; revise the
            administrative citation appeal process; and make other minor technical changes; amending Article
            22 (Parking Stations; Revenue Control Equipment) to clarify that non-City governmental entities
            operating parking stations are exempt from the revenue control equipment requirements; and
            amending the San Francisco Police Code Article 17 (Miscellaneous License Regulations) to clarify
            that governmental entities operating parking garages or parking lots are exempt from the permitting
            requirements applicable to other commercial parking garage and valet operations.
            PASSED, ON FIRST READING by the following vote:
                 Ayes: 11 - Avalos, Campos, Chiu, Chu, Cohen, Elsbernd, Farrell, Kim, Mar, Olague, Wiener


121012 [Adopting CEQA Findings - Geary Road Bridge Project]
            Resolution adopting findings under the California Environmental Quality Act (CEQA), CEQA
            Guidelines, and San Francisco Administrative Code Chapter 31, including the adoption of a
            mitigation monitoring and reporting program, related to the funding of Project No. CUW26403, the
            Geary Road Bridge Project, in Alameda County and directing the Clerk of the Board of Supervisors
            to notify the Controller of this action. (Public Utilities Commission)
            ADOPTED by the following vote:
                 Ayes: 11 - Avalos, Campos, Chiu, Chu, Cohen, Elsbernd, Farrell, Kim, Mar, Olague, Wiener




City and County of San Francisco                          Page 6                                Printed at 3:07 pm on 12/12/12